VTG Rail Logistics’ latest special transports in Eastern Europe and Russia

VTG moved a high pressure blowdown vessel with dimensions 2000 x 560 x 580 cm, 175 mt from Yekaterinburg to Tobolsk for an ongoing petrochemical plant project.

Transport preparations started one year ago with intensive road studies and bridge calculations while the final permit process lasted three months.

The cargo travelled 650 km in 8 days, passing 4 railway crossings as well as more than 60 bridges. VTG started with 16 axle modular trailer and had to extend half way to a 24 axle modular trailer to solve issues with one major bridge.

This project consisted of a single supplier with deliveries to two different customers:
Project details:

  • 925 freight tons for the erection of a refinery in Afipsky, Russia
  • 25 special transport consignments and more than 100 truck loads to Grodno, Belarus, for an air separation plant

Between July and September 2017, VTG Rail Logistics’ Project Solutions department delivered parts to Eastern Europe for the construction of two major plants. A global leading gas and engineering company and long-standing VTG customer is currently supplying parts for a refinery in Afipsky in the southwest Russian region of Krasnodar, as well as for an air separation plant in Grodno, Belarus. Read more…