This project was loaded from Busan port in three shipments totaling 2,908cbm.
In August the 1st shipment (1,064cbm) and 2nd shipment (731cbm) were delivered safely to the job site in Johor, Malaysia by Tera Projects and Shipping (CLC Projects member in Malaysia).
The last shipment (1,113cbm) is waiting for loading on the vessel at Busan port. All packages, including the biggest piece of 10.46m x 4.56m x 4.58m have been stuffed into containers. The shipment will be loaded on Aug. 20th, and will arrive at Pasir Gudang port around September 3rd.
After discharging at Pasir Gudang port, Tera Projects will arrange all delivery procedures up to the job site.