Procam Logistics performed the installation of a lathe machine using their own four point jack lifting system

The uneven load distribution of the Lathe Machine the clearance level of the room being ~ 7 meters made crane operations impossible.

Shifting operation was conducted using a two-point lifing system up to the point where the space could be made for the positioning using a four point lifting system.

The final shifting, placement and alignment was done using a four-point lifting system.

Procam Logistics Pvt. Ltd. is a member of CLC Projects representing India (New Delhi)

View profile: Procam Logistics Pvt. Ltd.