The 10km inland transit took 4 hours, the entire site operation spanned 2 days following 3 weeks of meticulous planning.
Preparation: 3 weeks of technical assessments and route surveys.
On-Site & Transit: 2 days of rigging and staging, including 1:00 AM transport via 13-axle hydraulic lines trailer to avoid traffic and ensure maximum safety.
Extraction & Launch: Dual-lift out of the factory & Port using 2 x 100-ton cranes.
Launch: Successful delivery into the river using 2 x 100-ton cranes with reinforced steel plates to spread out ground pressure on the Quay.
Execution is only as strong as the preparation, planning and coordination of Teamwork. Check out the video!