Mercomar Performed Inland Transport and Mounting of a Turbine, Generator and Condenser for the Central Cogeneracion Project

Mercomar's-latest-Project

Equipment: Turbine, Generator & Steam Condenser + Accesories

Scope of Work:

  1. Inland transportation from Terminal Zarate, Zarate (120 km aprox from Buenos Aires) to Central Térmica San Lorenzo (San Lorenzo, Sta Fe).
  2. Mounting turbine, generator and condenser at final site.

Main Pieces:

  • Turbine: 182 tons /// 8938 x 5300 x 4776 mm (L x W x H)
  • Generator: 134,1 tons /// 8900 x 4160 x 3570 mm (L x W x H)
  • Condenser: 72 tons /// 11600 x 4720 x 4800 mm (L x W x H)
  • Condenser Accessories: 16 tons /// 5880 x 4800 x 4800 mm (L x W x H)

Transportation Equipment Used:

  • Hydraulic Conventional Module (13 axes) – 1 Trip
  • Hydraulic Conventional Module (16 axes) – 1 Trip
  • Mechanic Low Bed (80 tons) – 1 Trip
  • Hydraulic Module – 1 Trip
  • Mechanic Low Bed (40 tons) – 2 Trips
  • Semi-Trailer (IMO Cargo) (28 tons) – 1 Trip
  • Semi-Trailer Gral Cargo (28 tons) – 13 Trips

Mounting Equipment Used:

  • ALE Heavy Lift Hydraulic Gantry TLG1000 – 1 Trip
  • Semi-Trailers Gral Cargo (28 tons) – 12 Trips

Mercomar is a member of CLC Projects representing Argentina, Bolivia, Paraguay & Uruguay